Electrical engineering: As general contractor for a ship painting shop in Croatia, All Engineering has taken over the planning and execution of the electronic building equipment on behalf of Thyssen Krupp. The acceptance of the installations also fell into the area of All Engineering.
Low-voltage and high-voltage systems were used. The installations must be installed in an explosion-proof manner.
Project: Ship painting shop in Rijeka
Description: Electrical installation of a painting - and spraying hall. Low-voltage systems, high-voltage systems including explosion-protected area with explosion-protected lights, sockets, etc.
Project volume: 3 million Euro
Client: Thyssen Krupp
Construction start: March 2001
Construction time: 6 Months
General Constructor: All Engineering
All Engineering Contract: We have taken over the complete planning in our area of responsibility, as well as the complete acceptances.
Special features: Quick execution to meet the deadline.