Electrical engineering: All Engineering plans and installs a new fire alarm system for the OSCE (Organization for Security and Co-operation in Europe) in 2000. Since the headquarters is occupied during the day, most of the assembly work must be carried out after the end of the service

  • Client: OSCE - Vienna

  • Construction start: July 2000

  • Construction time: 3 months

  • All Engineering Contract: Complete new installation of the entire fire alarm control panel from the manufacturer Esser. Including the complete power network, hand detector, central office, etc.

  • Special features: The OSCE building continued to operate throughout the installation. Most of the work had to be done after the end of the service.