New Faculty of Economics in Pristina, Kosovo
Electrical engineering: In 2000, All Engineering installed or commissioned all electrical engineering of the building for the new Faculty of Economics in Pristina on behalf of the OSCE. Some of the old installations can be used further. However, the entire computer installation and communication technology must be renewed.
Project: New Faculty of Economic in Pristina
Client: OSCE (Organization for Security and Co-operation in Europe)
Description: Reinstall or put into operation the complete electrical engineering installation.
Construction start: June 2000
Construction time: 4 months
General constractor: Co. Bautech GmbH
All Engineering Contract: Check old technology. Take over still usable technology, otherwise reinstall.
Complete computer technology, telephone and lighting technology.Special features: Very short execution period in an unstable country.