Airport in Irkutsk,1994
Fire prevention and protection: In the existing Aeroflot hangar of the Irkutsk airport All Engineering could demonstrate flexibility and problem-solving competence. This huge facility had to be equipped with state-of-the-art fire alarm and fire extinguishing systems. The problem was that the water reservoir was 800 meters away from the hangar, so adequate pipe heating had to be included to prevent the water from freezing on its way to the scene.
Project: Airport in Irkutsk
Description: Existing Aeroflot hangar (100x60x28 meters) had to be equipped with state of the art fire alarm and fire extinguishing systems.
Project volume: 6 million DM
Client: Ing. Office Friedland – Kreft
Construction start: November 1994
Period of installation: 3 Months
General Constructor: Various
All Engineering Contract: Planning of fire alarm system and automatic fire control.
Special features: Very special planning was needed for the extinguishing system because of specific problems caused by the enormous size of the hangar. As the water reservoir was 800 meters away, adequate pipe heating had to be included to prevent freezing at extreme minus temperatures.